How Adhesive OEM Production Works

Eight stages from enquiry to container, what we need from you at each one, and where it actually stalls — which is almost never in production.

Last updated: 2026-09-07

Three to four months, and the hold-up is usually paperwork

Production takes 15-25 working days and is the most predictable stage in the whole sequence. What runs late is artwork compliance, courier and dangerous-goods arrangements, and trial results that arrive without enough detail to act on.

All three are things the buyer owes the supplier, which is why they are worth knowing about in advance. Start the labelling work during your trial, not after you place the order.

1.Enquiry and specification

Answered within 24 hours

We need from you

Substrate pair, the condition that governs in service, volume, destination market and pack format.

We do

Identify whether an existing grade fits or a formulation is needed, and quote against it.

Where it stalls: An enquiry that asks only for a price list. Without the substrate and the market we can send numbers, but not an answer.

2.Sample

5-7 working days to produce

We need from you

A courier account or agreement to prepay freight, and the destination — samples of solvent-borne product ship as dangerous goods.

We do

Produce the sample, send the technical and safety data sheets, and tell you what to look for in the trial.

Where it stalls: Waiting on a courier account. Sort this out at enquiry stage rather than after the sample is made.

3.Your trial

Yours — commonly 2-4 weeks

We need from you

The result, including the failures. A trial that "did not work" without detail costs another round.

We do

Interpret the result and adjust, or tell you the chemistry is wrong for the job rather than iterating on a dead end.

Where it stalls: The longest and least predictable stage, and the one most often left out of a buyer’s own schedule.

4.Formulation work, if needed

2-4 weeks

We need from you

A frozen brief. Changing the target mid-development restarts it.

We do

Lab formulation, bench testing, revised sample. Qualification programmes with third-party testing run 4-6 weeks, excluding customer-side testing and third-party certification.

Where it stalls: Skip this entirely if an existing grade fits — most requirements are met by something already in the range.

5.Artwork and packaging

Runs in parallel — allow 2-3 weeks

We need from you

Print-ready artwork, and confirmation that it complies with your market’s hazard labelling law. That compliance is yours, not ours.

We do

Supply hazard classification and safety data for the label, produce a pre-production sample for approval.

Where it stalls: The single most common cause of delay. Start it during the trial, not after the order.

6.Production

15-25 working days after artwork approval

We need from you

Deposit per agreed terms — 30% T/T deposit, 70% balance against copy of B/L.

We do

Raw material procurement, batch production, filling, in-process and final QC, batch records retained.

Where it stalls: Rarely. Production is the most predictable stage in the whole sequence.

7.Documentation and dangerous goods

Concurrent with production

We need from you

Your forwarder’s details and confirmation that your port accepts Class 3.

We do

Certificate of analysis for the batch, SDS in the destination language, dangerous goods packaging certification and IMDG declaration.

Where it stalls: A forwarder who has not handled Class 3 before. Establish this at stage 1, not here.

8.Shipping

18-22 days to Southeast Asia, up to 35-55 days to Latin America

We need from you

Balance per terms.

We do

Container loading, FOB, with CIF and DDP on request.

Where it stalls: Peak season and dangerous-goods consolidation limits. On hot routes, remember the voyage consumes part of the shelf life.

Start these three now, whoever you end up buying from

  1. 1.Label compliance review. Longest lead time, least visible, and the only one where getting it wrong makes a whole container unsaleable.
  2. 2.A forwarder who handles Class 3. Ask them directly, before you need them. A forwarder discovering dangerous goods on your shipment is an expensive way to find out.
  3. 3.A written trial protocol. Decide what you will measure and what counts as a pass before the sample arrives, or the result will be an opinion rather than data.

Frequently asked questions

How long does an adhesive OEM order take from first enquiry?
For an existing grade with your label: allow roughly three to four months. Sample in 5-7 working days, your trial two to four weeks, artwork and compliance two to three weeks running in parallel, production 15-25 working days after artwork approval, then the sea leg. Add 2-4 weeks if the chemistry has to be developed, and considerably more for a formal qualification programme. Reorders against approved artwork and formulation are much shorter at 15-20 working days.
What causes delays in an adhesive OEM programme?
Three things, in order of frequency. Artwork and labelling compliance, which buyers start after the order rather than during the trial. Courier accounts and dangerous-goods arrangements for samples and shipment, which get discovered late. And trial results that arrive without enough detail to act on — "it did not work" costs a full extra round. Production itself is the most predictable stage in the sequence and is rarely the problem.
What do I need to provide for an OEM adhesive order?
At enquiry: the substrate pair, the condition that governs in service, volume, destination market and pack format. For samples: a courier account or agreement to prepay, since solvent-borne samples ship as dangerous goods. For production: print-ready artwork with your own confirmation that it meets your market’s hazard labelling law, the deposit, and your forwarder’s details. The labelling compliance is the item to start earliest — it holds up more programmes than anything else.
Can I visit the factory during production?
Yes, and for a significant programme it is worth it. A video walk of the line answers most of the same questions at no cost though — ask to see the reactor or mixing vessel, the filling line for your pack format, the QC laboratory and the warehouse in one continuous shot rather than as separate clips. What you are verifying is that the equipment matches the capability described in writing.
What quality documentation comes with an OEM shipment?
A certificate of analysis for the batch shipped, technical and safety data sheets for the exact grade, and for solvent-borne product the dangerous goods documentation including UN number, packing group and IMDG declaration. Depending on market we add a REACH SVHC statement and a VOC content statement against the instrument your specification names. Batch records and retained samples stay with us and are available if a bond is ever questioned — which is the practical difference between buying from a manufacturer and buying from a trader.
What is the minimum for a first OEM order?
Our liquid production minimum is 500 kg and aerosol is 2,000 cans, with trial quantities from 200 kg before you commit. Private label follows the standard MOQ of the selected product. Custom printed cans are the exception at 5,000 cans, because the printing plate and can-printer minimum sit behind them rather than our filling line.

Before and after the production run

Start at stage one

Substrate pair, governing condition, volume, destination and pack format. Send those five and you will get an answer rather than a price list — within 24 hours.